Holders of the DCDC certification are recognized as experts in data center design and are highly valued by employers in the ICT industry. They are able to design data centers that meet the needs of their organizations, while also ensuring that they are reliable, secure, and energy-efficient. BICSI Data Center Design Consultant - DCDC certification is also a valuable asset for consultants and contractors who work with data center clients.

 

NEW QUESTION # 61
What are three reasons for locating the power distribution unit outside the computer room?

  • A. reduces cable congestion, prevents water damage, provides better access points
  • B. removes maintenance item, removes a source of heat, allows P D U to occupy less expensive space
  • C. lowers electricity costs, improves network speed, enhances security measures
  • D. increases cooling efficiency, eliminates fire hazard, minimizes noise pollution

Answer: B


NEW QUESTION # 62
What level should the battery room be on?

  • A. Lower Floor
  • B. Upper floor
  • C. All
  • D. None
  • E. Grade Level

Answer: E

Explanation:
Explanation


NEW QUESTION # 63
where should printers be located

  • A. in a dedicated print room with dedicated air handling system
  • B. beside high traffic areas
  • C. near equipment that has active air flow to cool them down
  • D. placed outdoor, away from building facilities

Answer: A


NEW QUESTION # 64
What are the minimum separation distances for electrical and telecom services pathways to maintain from their primary and redundant feeds?

  • A. 15 meters (49 feet)
  • B. 10 meters (33 feet)
  • C. 20 meters (66 feet)
  • D. 5 meters (16 feet)

Answer: C


NEW QUESTION # 65
What is the minimum raised floor height?

  • A. 18"
  • B. 12"
  • C. 24"
  • D. 6"

Answer: A


NEW QUESTION # 66
What is the recommended clearance space required for hot and cold aisles in a data center?

  • A. 1-2 feet
  • B. 7-8 feet
  • C. 5-6 feet
  • D. 3-4 feet

Answer: D


NEW QUESTION # 67
what is the second preference regarding utility service

  • A. One balanced feeder coordinated with upstream backup feed
  • B. At least One Circuit from two Separate Substations and Different Voltage Levels
  • C. At least four circuits each from different distribution stations but fed via common feeders
  • D. Two balanced feeds with different voltages derived from a single distribution station

Answer: D


NEW QUESTION # 68
what is another main function of the entrance room?

  • A. to house the telecommunications main grounding busbar
  • B. to store backup telecommunication devices
  • C. as a dedicated location outside building
  • D. None of these

Answer: A

Explanation:
Explanation


NEW QUESTION # 69
What should be done with unused rack space?

  • A. they should be turned off to save energy costs
  • B. it should be left open to allow for better ventilation
  • C. it should be filled with blanking devices to reduce non-functional airflow
  • D. it should be used for additional storage purposes

Answer: C


NEW QUESTION # 70
What is the formula to find the maximum allowable cable depth in a non-solid bottom cable tray?

  • A. H = 150/1 + (L * 0.0007)
  • B. H = 50/1 + (L * 0.0007)
  • C. H = 100/1 + (L * 0.0007)
  • D. H = 200/1 + (L * 0.0007)

Answer: A


NEW QUESTION # 71
What is the appropriate fire rating requirements for a critical media storage room?

  • A. 1 hour
  • B. 3 hours
  • C. 2 hours
  • D. 4 hours

Answer: C


NEW QUESTION # 72
what is the ANSI/TIA-942 typical range of pressure differential regarding positive pressure for data center.

  • A. Less than or equal to -0,1 in water column (-25 Pa)
  • B. More than +3in wc (>746Pa),but less than or equaltto+6,in wc(1492 pa))
  • C. More than -0,005 in wc (< -1,24 Pa), but less than or equal to +0,05in wc (+12,4 Pa)
  • D. Less Than -4,+4 inches water column(-1000 opa ,+100 <pa>)

Answer: A


NEW QUESTION # 73
what is the most common energy storage solution and what are the two types

  • A. Lead-acid battery, vented and valve regulated
    Nickel-cadmium battery, vented and valve regulated
  • B. Lithium-ion battery, sealed and unsealed
  • C. Flywheel, vertical and horizontal
  • D. Supercapacitor, cylindrical and prismatic

Answer: A


NEW QUESTION # 74
where should the vendor storage area be located?

  • A. offsite
  • B. inside data center
  • C. adjacent or near secured loading dock
  • D. far away from loading dock

Answer: C


NEW QUESTION # 75
What is the first preference regarding utility service, class F4?

  • A. One circuit from one substation, separate paths
  • B. At least two circuits from one substation, same path
  • C. At least two circuits from two separate substations, diverse substation power grids and separate paths
  • D. At least one circuit from two separate substations, different voltage levels

Answer: C


NEW QUESTION # 76
where is the storage room located?

  • A. outermost point of Data Centre
  • B. All
  • C. away from computer room, adjacent to equipment entrance at data center
  • D. Near Backup Generator
  • E. next door to computing area

Answer: C


NEW QUESTION # 77
What types of electrical equipment is typically located inside the computer room

  • A. Circuit Breakers only
  • B. power distribution units, not power distribution equipment, remote power panels, and power strips
  • C. Uninterrupted Power Supply (UPS) only
  • D. transformers only

Answer: B

Explanation:
Explanation


NEW QUESTION # 78
What is the recommended floor loading capacity for a data center?

  • A. 1000 lbs per sq. ft.
  • B. 1250 lbs per sq. ft.
  • C. 1750 lbs per sq. ft.
  • D. 1500 lbs per sq. ft.
  • E. 2000 lbs per sq. ft.

Answer: D


NEW QUESTION # 79
What is the minimum distance recommended between a data center's backup generator and the main data center building?

  • A. 20 feet
  • B. 30 feet
  • C. 40 feet
  • D. 10 feet

Answer: B


NEW QUESTION # 80
What is the recommended placement of electrical distribution sub systems

  • A. install within the computer room space on raised floor
  • B. install within server racks
  • C. none of the above
  • D. install in dedicated electrical rooms, or, locate outside the computer room with fire rated wall

Answer: D

Explanation:
Explanation


NEW QUESTION # 81
......


BICSI DCDC-002 is a certification exam that is designed to test the skills and knowledge of data center design consultants. DCDC-002 exam is administered by BICSI, a professional association that serves the information and communications technology (ICT) industry. Passing DCDC-002 exam is a prerequisite for obtaining the BICSI Data Center Design Consultant (DCDC) credential.


BICSI DCDC-002 Certification Exam is a highly sought-after certification for professionals who specialize in the design and implementation of data centers. BICSI Data Center Design Consultant - DCDC certification exam is offered by BICSI, a leading professional association for the information and communications technology (ICT) industry. The DCDC certification is designed to help professionals develop an in-depth understanding of the design, implementation, and management of data center infrastructure.

 